Challenges of the procurement selection process

Optimal project outcomes are more likely to be achieved where an objective assessment of the most suitable procurement option is made based on the characteristics of the project. Key challenges include:

 poor planning and risk assessment. In some instances, poor project planning and/or risk assessment has resulted in inadequate consideration of key points required to ensure optimal project outcomes;

 timeframe pressures emerging for projects. Sometimes time pressures lead governments to make premature procurement decisions.  Even where adequate consideration is given to procurement analysis, sometimes delivery timeframes can unduly influence procurement decisions;

 market sentiment. At various times, a certain method may be preferred either in the public sector or private sector. Procurement methodology should be selected based on the necessary upfront analysis and planning to ensure that the project is successful; and

 focus not on value for money drivers. Projects should be objectively assessed against all the feasible procurement options, and a decision should be based on the option that is likely to deliver the best overall project outcomes, rather than one which contractors prefer, or the department or agency can proceed with simply or quickly.

Table 3 below sets out some of the key factors to consider in the various models.

Table 3: Suitability criteria and drivers of value

 

When to use (e.g. suitability criteria)

Value for money drivers

PPP

 Complex and long-term infrastructure projects

 Outputs can be clearly defined and measured

 Scope for innovation

 Whole-of-life asset management is achievable and cost-effective

 Strong market interest

 Opportunities for appropriate risk transfer

 Opportunity for bundling contracts

 Significant service component

 Complementary commercial development

 Sufficient scale and long-term nature

 Complex risk profile and opportunity for risk transfer

 Whole-of-life approach from integration of design, construction, operation and maintenance over the life of an asset, in a single project package

 Innovation

 Appropriate third-party use of facilities, reducing net cost to government

 Efficiency of contract management

Alliance

 Complex and high-risk infrastructure projects

 The solution is unclear or there is a significant likelihood of scope changes

 A high level of innovation is required

 Risks are unpredictable and best managed collectively, with costs of transferring risk prohibitive

 The owner can be closely involved and add value

 Cost of adversarial conduct, claims and disputes is eliminated (e.g. the "no blame" culture)

 Culture promotes innovation

 Integrated planning, design and construction process with early contractor and consultant involvement

Construct Only

 The scope is defined and there is little likelihood of scope creep or wholesale changes to requirements

 Little incentive or need for innovation from the contractor

 It is desirable and there is sufficient time to complete design documentation before tendering

 Limited opportunity for bundling services/maintenance and creating whole-of-life efficiencies

 Larger pool of potential tenderers which leads to increased competition

 Greater scope for competitive prices because of design certainty

 Contract value is set before construction starts

Design & Construct

 The government's requirements are tightly specified before tender or do not change

 Government is best-placed to manage most project risks

 Limited opportunity for bundling services/maintenance and creating whole-of-life efficiencies

 Single point of accountability for design and construction

 Fixed price contract

 Potentially, reduced overall project cost because the Contractor has the opportunity to contribute construction experience into the design, resulting in innovation and efficiencies

Managing Contractor

 Complex or high-risk projects with uncertain scope, risks or technology

 A degree of expert government input is available

 Early contractor involvement is beneficial

 Flexibility in delivery to manage uncertain risks

 Maximising government input to manage risks where appropriate

 Managing contractor is incentivised to achieve cost and schedule targets