3.5  Project Alliancing

In project alliancing government collaborates with one or more non-owner parties (e.g. a designer and constructor) to share the risks and responsibilities in delivering the construction phase of a project. All project delivery risks are shared by the alliance participants. The alliance contract and supporting structures promote a positive culture based on "no-fault, no-blame" and unanimous decision-making, and requiring all participants to find "best for project" solutions. Because the behavioural culture is crucial to the success of alliancing, the selection of the right participants is paramount.

Figure 8:  Simplified Alliance Structure

Under an alliance model, the non-owner parties are typically guaranteed reimbursement of their direct project costs and payment of corporate project overheads in an open-book arrangement. Targets for cost, schedule and other key parameters are developed jointly during the pre-construction phase. If actual delivery is better than the agreed targets, all parties share the reward ("gain-share"). Conversely, if delivery does not meet agreed targets, the pre-agreed "pain share" formula applies.

The following table lists features of an alliance -

Advantages

Disadvantages (and issues that may need managing)

 All parties have shared responsibility for ensuring design is appropriate

 Provides flexibility to modify design and allows on-going changes to be incorporated during construction

 Provides incentives to all parties to complete the project on time and within budget under the "gain-share, pain-share" philosophy

 Cost of adversarial conduct, claims and disputes is eliminated, in the  "no-blame" culture

 Can deliver highly complex projects with uncertain risks which would otherwise be extremely difficult or impossible to deliver

 Culture promotes innovation e.g. technical, safety, environmental

 Project management efficiencies through integrated management and elimination of all claims

 Stakeholder issues can be well managed through an alliance

 There is an integrated planning, design and construction process with early contractor & consultant involvement

 All parties commit to finding "best for project" solutions

 Potential for greater job satisfaction and skill enhancement for personnel involved

 Ability to attract greater number of tenderers for complex projects

 Less tender price competition and related certainty demonstrating value for money (unless multiple Target Out-turn Cost approach is used)

 Requires all parties to be genuinely committed to openness and collaboration - relies on success of relationships, teamwork and individuals' performance

 Requires on-going involvement of appropriately senior staff with authority to resolve issues - may require extra departmental input

 Cost to establish and maintain relationships can be high

 Limited alliance experience to date for building projects in the public sector (though commonly used for civil engineering, road, rail and water projects)

 The government bears the cost risk and other unspecified risks

 Overall design and fit-for-purpose risk lies with the government

 Government's recourse in the event of catastrophic failure is limited

 Lack of focus on lifecycle costs and considerations

Project alliancing should generally be considered only:

 in the delivery of complex and high-risk infrastructure projects;

 where the solution is unclear;

 where a high level of innovation is required;

 where risks are unpredictable and best managed collectively; and

 if the owner can be closely involved and add value.

Generally alliancing is not appropriate where risks can be identified and understood.