3.6  Managing Contractor

This form of contracting involves the principal appointing a head contractor (the managing contractor) who engages subcontractors to deliver the works.  The managing contractor is responsible for administering these subcontracts and accepts some delivery risk.  The principal and the managing contractor generally negotiate a fixed lump sum management fee.  The managing contractor may also receive incentive payments for achieving cost and schedule targets.  The managing contractor is engaged early in the process to manage the scope definition, design documentation and construction of the works.  The managing contractor sometimes performs elements of the design and/or construction and is paid for that in addition to the management fee.

The managing contractor typically:

 is paid a management fee and incentive payments for achieving target price, schedule and other key parameters;

 undertakes some or all of the design activities;

 may perform some of the construction works but does not necessarily do so;

 is responsible for preliminaries (e.g. crane hire, site sheds, supervision services etc), general project requirements (e.g. security, insurances etc) and project management (e.g. scheduling, coordinating, liaising, monitoring, reporting etc.);

 prepares the trade packages and conducts the tenders, selects suppliers in close collaboration with the client;

 warrants the quality of all works; and

 warrants the completion of the works by the date for Practical Completion. In general, this model is considered only:

 for complex or high-risk projects with uncertain scope, risks or technology;

 where a high degree of expert government input is available; and

 where early contractor involvement is beneficial.

Sometimes the managing contractor engages suppliers as subcontractors and is responsible for paying them. This variation of the managing contractor model is more like a construct only or design and construct arrangement and may be preferred depending on the risk allocation, payment and incentive structure considered to be most appropriate. Variants to the generic model have been developed by some jurisdictions to overcome the main disadvantages of the generic model described in these guidelines.  An example of such a variant currently in use is the two-stage design, novate and construct, guaranteed maximum price approach.

The following table lists features of the managing contractor model -

Advantages

Disadvantages (and issues that may need managing)

 Potential for shorter design and construction program as construction can commence during design development

 Allows government to retain control of the design development stage which means the government's requirements can be accommodated within specific designs rather than a functional specification

 The managing contractor can advise the design team on building issues during the design development process which facilitates integrated planning of construction and operations

 Allows early involvement of all project participants and stakeholders

 Reduces demand on departmental project management resources

 Risk of documentation lies with contractor

 Often has mechanisms for resolving issues and sharing benefits

 The fixed lump sum is typically negotiated not competitively tendered

 The government and the contractor share the risk of time and cost until the end of design development

 More risk to department for cost, time, design and not achieving best value-for-money outcome

 Difficulty setting cost targets with limited design details

 Time and cost overruns can be expensive where the design is not fully agreed and documented prior to construction commencement (construction holding costs can be expensive).

 Overall design and fit-for-purpose risk lies with the government

 Limited number of potential suitable tenderers may lead to higher cost in management margins

 Lack of focus on lifecycle costs and considerations