Risk Category | Description | Consequence | Mitigation | Preferred allocation |
Industrial relations | ||||
Industrial relations and civil commotion | The risk of strikes, industrial action or civil commotion causing delay and cost to the project. | Cost and time delay. | The private party or its subcontractors can manage this risk through the way it manages project delivery and operations. | Private party, except to the extent that government grants relief or extensions of time. |