9.1  Design obligations

(a)  The private party must design the facility so that the facility (when complete) will be fit for the intended purposes.

(b)  The private party is not relieved of any of its design obligations by sub-contracting any of the design works to a design consultant.  Issues associated with sub-contracting are dealt with in Chapter 28 (Sub-contractors).