19.1  Definition of Modification

(a)  "Modifications" will be defined on a project by project basis but will generally include:

(i)  in the design and construction phase, changes to the Design Requirements; and

(ii)  in the operating phase, changes to the facility or the Contracted Services,

but will not include:

 minor changes to the facility where 'minor' may be defined with reference to an agreed monetary threshold and/or defined as being works of a non-structural nature which are requested by government and do not result in a delay to Completion, including any Minor Works as outlined in section 19.8;

 the development and refinement of the design documentation in accordance with the project agreement; or

 any other changes to the works, facility or Contracted Services required to ensure the facility is fit for its intended purposes.