28.3 Amendments to material sub-contracts
(a) The main construction and operation sub-contracts (to be determined on a project by project basis) are not to be amended, terminated, assigned or replaced without government's prior written consent.
(b) The other material sub-contracts are also not to be amended, terminated, assigned or replaced without government's prior written consent where such amendment may impact on government's rights or the ability of the private party to satisfy its obligations under the project agreement and associated documents.
(c) Where prior government consent is not required, the private party must give government prompt notice of the termination or material amendment of a material sub-contract.