Shared

Allocation

Category Codes

Risk

Timing

Description

Consequence

Rationale/Mitigation

Risk Expert

Probability

Consequence

@ Risk Distribution

@ Risk Discrete Distrib'n

 

 

 

 

 

 

 

 

Yes

No

Best

Most likely

Worst

Yes

No

 

Shared

S4

Environmental risk

C

Risk that the site is contaminated requiring significant expense to remedy.

Clean up costs which could result in delays.

Undertake a site contamination assessment. As this is a green field site located on the urban fringe, it is unlikely that contamination risk will be an issue.

 

22%

78%

2000

3500

6000

3896.3

0

0

 

D5

Lengthy detailed design time

C

Risk that detailed design time is longer than anticipated

Delay in works commencement or completion and cost increases.

 

 

36%

64%

8000

8500

10000

8897.7

0

0

 

D6

Local community protest

C

Risk of adverse reaction and protest from local community to the Project.

Delay in works commencement or completion and cost increases.

Allow sufficient time for community consultation.

 

15%

85%

1500

2000

4000

2597.8

0

0

 

D7

Local community protest

O

Risk of adverse reaction and protest from local community to the Project.

Delay in works commencement or completion and cost increases.

Allow sufficient time for community consultation.

 

15%

85%

1100

1200

1500

1279.5

0

0

 

SF5

Risk of obtaining insurance cover

L

Risk of inability to obtain insurance or material increases in insurance premiums eg, construction, third party, professional indemnity, collapse of insurance company, WorkCover.

Material increases in premiums priced into the bid by the Private Party or inability to obtain the relevant insurance.

This risk is shared due to the uncertain situation regarding insurance since September 11 2001, it is expected that availability of insurance will decrease or increases in premiums will occur.

 

44%

56%

2000

3000

5000

3396.7

0

0

 

SC13

Lengthy negotiation of changes to specifications

 

Risk of lengthy negotiations between stakeholders on what is a legitimate change to the service specifications.

Delay in works commencement or completion and cost increases.

Agree with all stakeholders a dispute resolution process.

 

 

 

 

 

 

 

 

 

 

SC14

Negotiation of changes to specifications

 

Risk of lengthy negotiations between stakeholders on what is a legitimate change to the service specifications.

Impact on Hospital Operator quality of service to patients of the Facility and increases in cost

Agree with all stakeholders a dispute resolution process.

 

 

 

 

 

 

 

 

 

 

SC15

Service required from private sector is higher than expected or does not meet expectations.

 

Risk that demand for private party services differs from the expected level, ie maintenance works are higher than expected due to unanticipated increase in patient demand

Increase in costs

The State will conduct a detailed service specification incorporating future projected changes in population where possible to ensure that unanticipated additional services/ facilities are kept to a minimum.

 

 

 

 

 

 

 

 

 

 

D15

Contamination or infection caused by inadequate design layout of clinical areas

 

Risk that the design or the layout leads to contamination or infection with regard to the clinical functionality of the area.

Impact on Hospital Operator quality of service to patients of the Facility and increases in cost.

Design of the building to be conducted by appropriately qualified experts and clinical functionality is to be endorsed by the State.

 

 

 

 

 

 

 

 

 

 

D16

Contamination or infection caused by inadequate design layout of clinical areas

 

Risk that the design or the layout leads to contamination or infection with regard to the clinical functionality of the area.

Impact on Hospital Operator quality of service to patients of the Facility and increases in cost.

Design of the building to be conducted by appropriately qualified experts and clinical functionality is to be endorsed by the State.

 

 

 

 

 

 

 

 

 

 

SF1

Foreign exchange rate movement -(medical equipment purchased overseas)

 

Risk of adverse movements in foreign exchange rates in relation to the purchase of medical equipment

Increase in cost

The Private Party can hedge their exposure to foreign exchange.

 

 

 

 

 

 

 

 

 

 

SF3

Risk of material changes in inflation.

 

Risk that the value of payments made/ received during the term is eroded by inflation

Diminution in real returns of the Private Party.

Private party takes the risk on the methodology adopted to maintain value, however the State shares risk to the extent of agreed indexation

 

 

 

 

 

 

 

 

 

 

L2

Change in law/policy

 

A change in Law which is limited in its application to any of the following: the Project, provision of publicly funded health care premises in Victoria, or other States within Australia including Victoria, or provision of health care accommodation services by the private sector to the public sector for operation as a publicly funded hospital in Victoria or other States within Australia including Victoria.

Adverse cost consequences in order to comply with the change.

This will be a shared risk depending on the nature of the change.

 

 

 

 

 

 

 

 

 

 

L14

Other authority changes

 

Risk of authority changes which impact for example, the design of cooling towers.

Adverse cost consequences in order to comply with the change. Impact on Hospital Operator operational service.

 

 

 

 

 

 

 

 

 

 

 

F1

Force Majeure

 

Risk of inability to provide any aspect of the Project caused by a force majeure event.

Delay and costs

The State will share in reinstatement costs with the private party to resume services.

 

 

 

 

 

 

 

 

 

 

F2

Force Majeure

 

Risk of inability to provide any aspect of the Project caused by a force majeure event.

Increase in costs

The State will share in reinstatement costs with the private party to resume services.