9. Tender requirements



Information on tender requirements is contained in the Commonwealth Procurement Rules.

As part of the RFP response, bidders should be requested to provide a compliance schedule which identifies all instances of departure from the draft contract, including providing the rationale and cost for each departure. Bidders should also be asked to submit a fully marked up contract and schedules outlining any instances of departure.

As part of the RFP response, bidders should be asked for evidence of committed finance at bid submission, unless specific project circumstances deem otherwise.