3. PPP as a procurement option
The National PPP Guidelines provide that projects with a total capital value exceeding $50 million should be considered for delivery as a PPP. South Australian agencies are also required to comply with Treasurer's Instruction 17 Evaluation of and Approvals to proceed with Public Sector Initiatives and the Guidelines for the Evaluation of Public Sector Initiatives which form part of that instruction.
The decision as to whether or not a project will be delivered as a PPP will be determined by Cabinet, on a project-by-project basis.