20.2.4 Mitigation
During the period of the suspension, the private party must use all reasonable endeavours to prevent or mitigate the effects of the Force Majeure Event and must take all reasonable steps in accordance with Good Industry Practice to overcome or minimise the consequences of the Force Majeure Event. This may include for example incurring reasonable expenditure, rescheduling resources and implementing appropriate temporary measures.