20.2.6  No financial relief



Government will not be obliged to provide any financial relief to the private party during the period of suspension (e.g. to meet the private party's fixed operating costs) or extend the Contract Term to take account of the period of suspension.73




_______________________________________________________________________________
73 However, see sections 15.1(b)(iv) and 20.3.2 in relation to Uninsurable Force Majeure Events.