27.8 No Relief to private party by sub-contracting obligations
The private party is not relieved of any of its obligations and liabilities under the project agreement as a result of sub-contracting any of the works or services or government's approval of any sub-contractor. The private party will, in each instance, be responsible for the sub-contractors' performance.